EIA Compliance: Reorganization of the National Grid in the area between Colunga and Ferrara - 132 kV power lines Colunga-Altedo, Altedo-Ferrara Sud, Ferrara Sud-Centro Energia

1394

12/01/2018

The EIA compliance determination (DVA-DEC-2018-0000008 of 12 January 2018) on the prescription A.1 of the EIA decision no.222 of 28 July 2016 related to the change of the work plan related to the reorganization of the National Grid in the area between Colunga and Ferrara - 132 kV power lines Colunga-Altedo, Altedo-Ferrara Sud, Ferrara Sud-Centro Energia has been issued with partly favourable outcome.

Go to the project

Download the determination