Procedure Code (ID_VIP/ID_MATTM): |
2777 |
Date of application submission: |
25/06/2014 |
Publication date of the notice in newspapers: |
20/06/2014 |
Deadline of submission of Public Comments: |
24/08/2014 |
Technical assessment starting date: |
04/07/2014 |
Date of request for integrations: |
29/05/2015 |
Date of integrations receipt: |
26/08/2015 |
Republication date of the notice in newspapers: |
27/08/2015 |
Deadline of submission of Public Comments on the republished project: |
26/10/2015 |
Republication subject
: |
Documentazione integrativa |
Date of integrations related to the republished project receipt: |
03/06/2016 |
Date of integrations related to the republished project second receipt : |
14/09/2016 |
Date of the Opinion of the National Technical Commission on usage Plan: |
31/08/2016 |
Opinion number of the National Technical Commission on usage Plan: |
2153 |
Opinion outcome of the National Technical Commission on usage Plan: |
Approvato con prescrizioni |
Usage Plan Determination date: |
28/11/2016 |
Determination number on usage Plan: |
DVA-DEC-2016-0000408 |
Usage Plan Determination outcome: |
Approvato con prescrizioni |
Date of the Opinion of the National Technical Commission : |
30/09/2016 |
National Technical Commission Opinion number: |
2182 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the EIA Decree: |
14/03/2017 |
EIA Decree number: |
DM-0000056 |
EIA Decree outcome: |
Positivo con prescrizioni |
Notes: |
Con nota del 11/06/2015 (prot.DVA-2015-0015380) è stata concessa una proroga di 45 giorni per la consegna delle integrazioni. |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |