Environmental Impact Assessment |
4949 |
22/10/2019 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4949 |
Subject
: |
Riqualifica con caratteristiche autostradali della S.P. 46 Rho-Monza dal termine della tangenziale nord di Milano (galleria artificiale) al ponte sulla linea ferroviaria Milano-Varese (compreso), corrispondente alle tratte 1 e 2 del "Progetto viabilità di adduzione al sistema autostradale esistente A8/A52 Rho-Monza" istanza di proroga D.M. 274 del 17/11/2014 che integra il D.M. 2 del 07/01/2014 |
Date of application submission: |
22/10/2019 |
Date of the Opinion of the National Technical Commission : |
23/07/2021 |
National Technical Commission Opinion number: |
138 |
National Technical Commission Opinion outcome: |
Positivo |
Ministry of Cultural Heritage and Tourism Opinion date: |
16/04/2020 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
MATTM_2020-0027001 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
Positivo |
Date of the EIA Decree: |
29/09/2021 |
EIA Decree number: |
DM_2021-0000403 |
EIA Decree outcome: |
Positivo |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Observatory |
|
30/01/2015 |
- |
Procedure details
|
|
Observatory setting up date: |
30/01/2015 |
Stage of the Procedure: |
- |
EIA Compliance |
2928 |
19/01/2015 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2928 |
Subject
: |
Prescrizioni: a, b,c del Decreto VIA n. 274 del 17/11/2014 e prescrizione A.24 del Decreto VIA n. 2 del 07/01/2014 |
Date of application submission: |
19/01/2015 |
Technical assessment starting date: |
21/01/2015 |
Date of the Opinion of the National Technical Commission : |
20/03/2015 |
National Technical Commission Opinion number: |
1747 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
25/03/2015 |
Determination number: |
DVA-DEC-2015-0000042 |
Determination outcome: |
Ottemperata |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
2800 |
18/07/2014 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2800 |
Subject
: |
Prescrizioni A.2,A.24,B.3 del Decreto VIA n.2 del 07/01/2014 |
Date of application submission: |
18/07/2014 |
Determination date: |
14/10/2014 |
Determination number: |
DVA-2014-0033078 |
Determination outcome: |
Parzialmente Ottemperata |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
2654 |
05/02/2014 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2654 |
Subject
: |
Prescrizioni A.2,A.3,A.4,A.5,A.6,A.8,A.9,A.13,A.15,A.24,A.25,B.3,B.4,B.6 del Decreto VIA n.2 del 07/01/2014 |
Date of application submission: |
05/02/2014 |
Determination date: |
13/06/2014 |
Determination number: |
DVA-2014-0018901 |
Determination outcome: |
Parzialmente Ottemperata |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment |
2028 |
05/09/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2028 |
Date of application submission: |
05/09/2012 |
Publication date of the notice in newspapers: |
05/09/2012 |
Deadline of submission of Public Comments: |
04/11/2012 |
Technical assessment starting date: |
24/09/2012 |
Date of the Opinion of the National Technical Commission : |
19/07/2013 |
National Technical Commission Opinion number: |
1301 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the EIA Decree: |
07/01/2014 |
EIA Decree number: |
DM-0000002 |
EIA Decree outcome: |
Positivo con prescrizioni |
Notes: |
Il Decreto VIA DM-0000274 del 17/11/2014 integra il decreto VIA DM-0000002 del 07/01/2014 |
Stage of the Procedure: |
Concluded |