New 132 kV T.745 power line "Fossano-Magliano Alpi"


General information

Work: 132 kV power line "Fossano-Magliano Alpi"

Project: New 132 kV T.745 power line "Fossano-Magliano Alpi"

Description: The project involves the construction of the single circuit 132 kV power line between the electrical substation of Fossano and electrical station of Magliano Alpi, 15,1 km long (4,25 km underground cable and 10,8 km overhead power line)

Developer: Terna Rete Italia S.p.A.

Project type: Electrical power lines

Territories and marine areas

Map

Regions: Piemonte

Provinces: Cuneo

Municipalities: Sant'Albano Stura, Trinita', Fossano, Magliano Alpi

Marine areas: None

Select procedure

Procedure Procedure Code Starting date Stage of the procedure
EIA Compliance 6100 28/04/2022 Concluded Procedure details Documents
Environmental Impact Assessment 2822 20/08/2014 Concluded Procedure details Documents