Work: 132 kV power line "Pontremoli - Edison Teglia" n.037
Project: 132 kv "Pontremoli - Edison Teglia" power line n.037 - Reconstruction project from support n.1 to support n.40
Description: The project involves the reconstruction of 132 kv "Pontremoli - Edison Teglia" power line in the section between the Edison Teglia power plant and the support n.40 about 6,6 km long.
Developer: Terna S.p.A.
Project type: Electrical power lines
Deadline for submission of comments: 25/11/2018 mail
Regions: Toscana
Provinces: Massa-Carrara
Municipalities: Pontremoli
Marine areas: None
Procedure | Procedure Code | Starting date | Stage of the procedure | ||
---|---|---|---|---|---|
EIA Screening | 4210 | 07/08/2018 | Concluded | Procedure details | Documents |