EIA Compliance |
8358 |
20/04/2022 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
8358 |
Subject
: |
Riassetto Rete Elettrica Nazionale nell'area tra Colunga e Ferrara. Elettrodotti a 132 kV: Colunga-Altedo; Altedo-Ferrara Sud; Ferrara Sud-Centro Energia - Prescrizioni: A.1, A.2, A.3 |
Date of application submission: |
20/04/2022 |
Date of request for documents perfection : |
06/05/2022 |
Date of perfection proceedings documents receipt: |
20/05/2022 |
Technical assessment starting date: |
01/06/2022 |
Date of the Opinion of the National Technical Commission : |
10/10/2022 |
National Technical Commission Opinion number: |
578 |
National Technical Commission Opinion outcome: |
Parzialmente ottemperata |
Determination date: |
11/10/2023 |
Determination number: |
MASE_VA_DEC_2023-0000473 |
Determination outcome: |
Ottemperata |
Notification date: |
17/10/2023 |
Notification Reference number: |
MASE_2023-0165937 |
Responsible of the procedure: |
Claudia Pieri - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment |
6107 |
16/04/2021 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
6107 |
Subject
: |
Riassetto Rete Elettrica Nazionale nell'area tra Colunga e Ferrara. Elettrodotti a 132 kV: Colunga-Altedo; Altedo-Ferrara Sud; Ferrara Sud-Centro Energia. Proroga del Decreto VIA DM 222 del 28/07/2016 |
Date of application submission: |
16/04/2021 |
Date of the Opinion of the National Technical Commission : |
20/05/2022 |
National Technical Commission Opinion number: |
267 |
National Technical Commission Opinion outcome: |
Positivo |
Ministry of Cultural Heritage and Tourism Opinion date: |
01/07/2021 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
22284 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
Positivo |
Date of the EIA Decree: |
09/08/2022 |
EIA Decree number: |
MiTE-VA-DEC-2022-0000177 |
EIA Decree outcome: |
Emanato Positivo |
Responsible of the procedure: |
Claudia Pieri - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
5636 |
03/11/2020 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
5636 |
Subject
: |
Riassetto Rete Elettrica Nazionale nell'area tra Colunga e Ferrara. Elettrodotti a 132 kV: Colunga-Altedo; Altedo-Ferrara Sud; Ferrara Sud-Centro Energia - Prescrizione: A.2 |
Date of application submission: |
03/11/2020 |
Technical assessment starting date: |
19/11/2020 |
Date of notification to the developer of the procedure outcomes: |
23/04/2021 |
Date of the Opinion of the National Technical Commission : |
06/04/2021 |
National Technical Commission Opinion number: |
224 |
National Technical Commission Opinion outcome: |
Parzialmente ottemperata |
Determination date: |
21/04/2021 |
Determination number: |
MATTM_DEC_2021-0000122 |
Determination outcome: |
Parzialmente ottemperata |
Notification Reference number: |
MATTM-2021-0042470 |
Outcome: |
Parzialmente ottemperata |
Responsible of the procedure: |
Claudia Pieri - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
4996 |
28/11/2019 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4996 |
Subject
: |
Riassetto Rete Elettrica Nazionale nell'area tra Colunga e Ferrara. Elettrodotti a 132 kV: Colunga-Altedo; Altedo-Ferrara Sud; Ferrara Sud-Centro Energia - Prescrizione: A.2 |
Date of application submission: |
28/11/2019 |
Technical assessment starting date: |
12/12/2019 |
Date of notification to the developer of the procedure outcomes: |
10/06/2020 |
Date of the Opinion of the National Technical Commission : |
28/02/2020 |
National Technical Commission Opinion number: |
3288 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
29/05/2020 |
Determination number: |
133 |
Determination outcome: |
Ottemperata |
Notification Reference number: |
43453 |
Outcome: |
Ottemperata |
Responsible of the procedure: |
Gianluigi Nocco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
4088 |
18/05/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4088 |
Subject
: |
Prescrizione A.1 del Decreto VIA n. 222 del 28/07/2016 - Procedura limitata all'Elettrodotto ex 220 kV "Colunga - Palo 130" - Comune di Minerbio - Variante aerea a seguito di interferenza con SNAM |
Date of application submission: |
18/05/2018 |
Technical assessment starting date: |
24/05/2018 |
Date of the Opinion of the National Technical Commission : |
22/06/2018 |
National Technical Commission Opinion number: |
2768 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
04/07/2018 |
Determination number: |
DVA-DEC-2018-0000296 |
Determination outcome: |
Ottemperata |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
3730 |
21/09/2017 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3730 |
Subject
: |
Prescrizione A.2 del Decreto VIA n. 222 del 28/07/2016 |
Date of application submission: |
21/09/2017 |
Technical assessment starting date: |
03/10/2017 |
Date of the Opinion of the National Technical Commission : |
09/02/2018 |
National Technical Commission Opinion number: |
2636 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
14/02/2018 |
Determination number: |
DVA-DEC-2018-0000073 |
Determination outcome: |
Ottemperata |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
3719 |
21/09/2017 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3719 |
Subject
: |
Prescrizione A.1 del Decreto VIA n. 222 del 28/07/2016 |
Date of application submission: |
21/09/2017 |
Technical assessment starting date: |
06/11/2017 |
Date of the Opinion of the National Technical Commission : |
18/12/2017 |
National Technical Commission Opinion number: |
2591 |
National Technical Commission Opinion outcome: |
Parzialmente ottemperata |
Determination date: |
12/08/2018 |
Determination number: |
DVA-DEC-2018-0000008 |
Determination outcome: |
Parzialmente ottemperata |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment |
2677 |
04/03/2014 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
2677 |
EIA-AA integrated Procedure : |
Sì |
Date of application submission: |
04/03/2014 |
Publication date of the notice in newspapers: |
28/02/2014 |
Deadline of submission of Public Comments: |
03/05/2014 |
Technical assessment starting date: |
11/03/2014 |
Date of request for integrations: |
26/06/2014 |
Date of integrations receipt: |
22/12/2014 |
Republication date of the notice in newspapers: |
18/12/2014 |
Deadline of submission of Public Comments on the republished project: |
16/02/2015 |
Republication subject
: |
Documentazione integrativa |
Date of the Opinion of the National Technical Commission : |
20/03/2015 |
National Technical Commission Opinion number: |
1746 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the EIA Decree: |
28/07/2016 |
EIA Decree number: |
DM-0000222 |
EIA Decree outcome: |
Positivo con prescrizioni |
Notes: |
Con nota del 13/11/2014 (prot. DVA-2014-0037288) viene concessa una ulteriore proroga di 45 giorni per la consegna delle integrazioni. Con nota del 06/10/2014 (prot. DVA-2014-0031977) è stata concessa una ulteriore proroga di 45 giorni per la consegna delle integrazioni. Con nota del 29/08/2014 (prot. DVA-2014-0027681) è stata concessa una proroga di 45 giorni per la consegna delle integrazioni |
Responsible of the procedure: |
Antonio Venditti - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |