ENEL Produzione S.p.A. Centrale a Ciclo Combinato di Porto Corsini

General information

Installation: ENEL Produzione S.p.A. Centrale a Ciclo Combinato di Porto Corsini

Localization: 48010 - Via Baiona 253 Porto Corsini

Description: Centrale a Ciclo Combinato di Porto Corsini

Installation type: Thermal power plant

Operator: Enel Produzione S.p.A.

Tax code: 05617841001

Installation status: Installazione in esercizio

Territories and marine areas

Regions: Emilia Romagna

Provinces: Ravenna

Municipalities: Ravenna

Marine areas: None

Select procedure

Procedure Procedure Code Starting date Stage of the procedure
IPPC permit for non substantial changes 37/16053 28/03/2024 on-going procedure Procedure details Documents
IPPC permit for non substantial changes 37/13957 19/01/2023 Concluded Procedure details Documents
IPPC permit’s reconsideration 37/13821 30/12/2022 Concluded Procedure details Documents
IPPC permit for substantial changes 37/13578 02/11/2022 Concluded Procedure details Documents
Reconsideration of compliance to permit conditions 37/13170 21/07/2022 Concluded Procedure details Documents
IPPC permit for non substantial changes 37/12923 10/06/2022 Concluded Procedure details Documents
IPPC permit’s reconsideration 37/12859 25/05/2022 Concluded Procedure details Documents
IPPC permit for non substantial changes 37/11676 09/07/2021 Concluded Procedure details Documents
Reconsideration of compliance to permit conditions 37/10571 31/12/2019 Concluded Procedure details Documents
IPPC permit’s reconsideration 37/10143 02/05/2019 Concluded Procedure details Documents
IPPC permit’s reconsideration 37/1118 17/01/2017 Concluded Procedure details Documents
Reconsideration of compliance to permit conditions 37/836 19/12/2014 Concluded Procedure details Documents
IPPC permit for non substantial changes 37/613 11/09/2013 Concluded Procedure details Documents
IPPC permit for non substantial changes 37/476 18/12/2012 Concluded Procedure details Documents
IPPC permit for non substantial changes 37/393 17/07/2012 Concluded Procedure details Documents
IPPC permit for non substantial changes 37/347 10/05/2012 Concluded Procedure details Documents
First IPPC permit for existing installation 37 04/10/2006 Concluded Procedure details Documents