IPPC permit’s reconsideration |
42/15621 |
16/01/2024 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/15621 |
Reference of previous authorization's Act: |
DM 0000092 del 14/03/2018 |
Ministry Protocol Application submission: |
prot. MASE/7900 |
Ministry Protocol date of application submission: |
16/01/2024 |
Subject: |
riesame parziale alla prescrizione n. 16 del decreto AIA prot. 92/2018 |
Procedure starting date : |
19/01/2024 |
Launch of public consultation: |
19/01/2024 |
Deadline of submission of Public Comments on IPPC permit: |
18/02/2024 |
Decision Number: |
MASE - 2024 - 047940 |
Decision Date: |
12/03/2024 |
Stage of the Procedure: |
Concluded |
IPPC permit’s reconsideration |
42/11560 |
19/05/2021 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/11560 |
Reference of previous authorization's Act: |
D.M. 92/2018 |
Ministry Protocol date of application submission: |
19/05/2021 |
Subject: |
Riesame parziale AIA a seguito attività di controllo ordinaria aprile 2021 |
Procedure starting date : |
05/07/2021 |
Decision Number: |
DM 92 |
Decision Date: |
22/02/2022 |
Date of notification to the developer of the procedure outcomes: |
02/03/2022 |
Notification Reference number: |
MITE-2022-26426 |
Outcome: |
POSITIVO |
Stage of the Procedure: |
Concluded |
IPPC permit’s reconsideration |
42/11123 |
27/11/2020 |
on-going procedure |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/11123 |
Ministry Protocol date of application submission: |
27/11/2020 |
Procedure starting date : |
11/12/2020 |
Launch of public consultation: |
26/01/2021 |
Deadline of submission of Public Comments on IPPC permit: |
25/02/2021 |
Decision Number: |
DM 305 |
Decision Date: |
27/07/2021 |
Decisions' Outcome: |
positivo |
Date of notification to the developer of the procedure outcomes: |
03/08/2021 |
Notification Reference number: |
MATTM-2021-85058 |
Outcome: |
POSITIVO |
Stage of the Procedure: |
on-going procedure |
IPPC permit for non substantial changes |
42/11032 |
25/08/2020 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/11032 |
Reference of previous authorization's Act: |
D.M. 92/2018 |
Application submission date: |
25/08/2020 |
Ministry Protocol Application submission: |
prot. MATTM-66103 |
Ministry Protocol date of application submission: |
25/08/2020 |
Subject: |
Progetto "Dimostrazione su scala industriale della tecnologia SCT (Short Contact Time) - CPO (Catalytic Partial Oxidation - Ossidazione Parziale Catalitica) - Progetto CPO Demo" |
Procedure starting date : |
27/10/2020 |
Decision Number: |
MATTM-2021-33717 |
Decision Date: |
31/03/2021 |
Decisions' Outcome: |
Positivo |
Date of notification to the developer of the procedure outcomes: |
31/03/2021 |
Notification Reference number: |
MATTM-2021-33717 |
Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
42/9676 |
26/09/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/9676 |
Reference of previous authorization's Act: |
DM 0000092 del 14/03/2018 |
Application submission date: |
26/09/2018 |
Ministry Protocol Application submission: |
DVA/21614 |
Ministry Protocol date of application submission: |
26/09/2018 |
Subject: |
Ottemperanza Prescrizione 1 |
Procedure starting date : |
08/10/2018 |
Decision Number: |
DVA/2019/12672 |
Decision Date: |
20/05/2019 |
Decisions' Outcome: |
Positivo |
Date of notification to the developer of the procedure outcomes: |
20/05/2019 |
Notification Reference number: |
DVA/2019/12672 |
Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
42/9677 |
26/09/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/9677 |
Reference of previous authorization's Act: |
DM 00000092 del 14/03/2018 |
Application submission date: |
26/09/2018 |
Ministry Protocol Application submission: |
DVA/21649 |
Ministry Protocol date of application submission: |
27/09/2018 |
Subject: |
Ottemperanza Prescrizione 11 |
Procedure starting date : |
08/10/2018 |
Date of notification to the developer of the procedure outcomes: |
21/02/2019 |
Notification Reference number: |
DVA/2019/4352 |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
42/9678 |
26/09/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/9678 |
Reference of previous authorization's Act: |
DM 0000092 del 14/03/2018 |
Application submission date: |
26/09/2018 |
Ministry Protocol Application submission: |
DVA/21643 |
Ministry Protocol date of application submission: |
27/09/2018 |
Subject: |
Ottemperanza Prescrizione 13 |
Procedure starting date : |
08/10/2018 |
Date of notification to the developer of the procedure outcomes: |
21/02/2019 |
Notification Reference number: |
DVA/2019/4350 |
Outcome: |
positivo |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
42/9679 |
26/09/2018 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/9679 |
Reference of previous authorization's Act: |
DM 0000092 del 14/03/2018 |
Application submission date: |
26/09/2018 |
Ministry Protocol Application submission: |
DVA/21639 |
Ministry Protocol date of application submission: |
27/09/2018 |
Subject: |
Ottemperanza Prescrizione 22 |
Procedure starting date : |
08/10/2018 |
Date of notification to the developer of the procedure outcomes: |
21/12/2018 |
Notification Reference number: |
DVA/2018/29111 |
Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
42/12414 |
19/02/2018 |
Administrative control |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/12414 |
Ministry Protocol date of application submission: |
19/02/2018 |
Subject: |
Validazione della Relazione di Riferimento |
Stage of the Procedure: |
Administrative control |
IPPC permit’s reconsideration |
42/1055 |
15/04/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/1055 |
Reference of previous authorization's Act: |
DVA-DEC-2010-273 e 274 |
Application submission date: |
08/04/2016 |
Ministry Protocol Application submission: |
DEC 127/DVA |
Ministry Protocol date of application submission: |
08/04/2016 |
Subject: |
Riesame complessivo |
Procedure starting date : |
15/04/2016 |
Decision Number: |
D.M. 92 |
Decision Date: |
14/03/2018 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
IPPC permit’s reconsideration |
42/1026 |
08/03/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/1026 |
Application submission date: |
05/01/2016 |
Ministry Protocol Application submission: |
94 |
Ministry Protocol date of application submission: |
05/01/2016 |
Subject: |
Relazione di Riferimento |
Procedure starting date : |
08/03/2016 |
Decision Number: |
30819/DVA |
Decision Date: |
21/12/2016 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
Reconsideration of compliance to permit conditions |
42/1047 |
19/02/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/1047 |
Application submission date: |
01/02/2016 |
Ministry Protocol Application submission: |
2273/DVA |
Ministry Protocol date of application submission: |
01/02/2016 |
Subject: |
Verifica prescrizionen. 6 del Parere Istruttorio Conclusivo prot. CIPPC-00-2015-0002560 del 22/12/2015 |
Procedure starting date : |
19/02/2016 |
Decision Number: |
DM 92 |
Decision Date: |
14/03/2018 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
IPPC permit for substantial changes |
42/884 |
21/04/2015 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/884 |
Application submission date: |
09/03/2015 |
Ministry Protocol Application submission: |
DVA-205-0006554 |
Ministry Protocol date of application submission: |
11/03/2015 |
Subject: |
Richieste di deroghe previste dalla parte V dell'allegato II parte I per gli impianti anteriori al 2002 |
Procedure starting date : |
21/04/2015 |
Decision Number: |
D.M. 318 |
Decision Date: |
30/12/2015 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
IPPC permit for substantial changes |
42/885 |
21/04/2015 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/885 |
Application submission date: |
04/03/2015 |
Ministry Protocol Application submission: |
DVA-2015-0006732 |
Ministry Protocol date of application submission: |
11/03/2015 |
Subject: |
Modifica sostanziale per nuovo assetto recupero vapori |
Procedure starting date : |
21/04/2015 |
Decision Number: |
DM 92 |
Decision Date: |
14/03/2018 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
42/677 |
20/01/2014 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/677 |
Application submission date: |
16/12/2013 |
Ministry Protocol Application submission: |
DVA-2013-0030522 |
Ministry Protocol date of application submission: |
31/12/2013 |
Subject: |
Modifica non sostanziale al nuovo assetto alternativo e reversibile di marcia per lunità integrativa RHU/HDC |
Procedure starting date : |
20/01/2014 |
Decision Number: |
DVA-2015-0014374 |
Decision Date: |
28/05/2015 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit’s reconsideration |
42/575 |
28/06/2013 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/575 |
Application submission date: |
28/06/2013 |
Ministry Protocol Application submission: |
DVA-2013-0015310 |
Ministry Protocol date of application submission: |
28/06/2013 |
Procedure starting date : |
28/06/2013 |
Date of request for integrations: |
09/10/2013 |
Decision Number: |
D.M. 92 |
Decision Date: |
14/03/2018 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
42/462 |
05/12/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/462 |
Application submission date: |
16/11/2012 |
Ministry Protocol Application submission: |
DVA - 2012 -0 028250 |
Ministry Protocol date of application submission: |
22/11/2012 |
Subject: |
Valutazione ottemperanze di prescrizione art.1, commi 3,4,5,6 e 7 del decreto AIA |
Procedure starting date : |
05/12/2012 |
Decision Number: |
DVA-2013-0016028 |
Decision Date: |
09/07/2013 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
42/407 |
31/10/2012 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/407 |
Application submission date: |
11/07/2012 |
Ministry Protocol Application submission: |
DVA - 2012 - 0019421 |
Ministry Protocol date of application submission: |
13/08/2012 |
Subject: |
Modifica non sostanziale all'impianto recupero vapori presso terminale marittimo |
Procedure starting date : |
31/10/2012 |
Date of request for integrations: |
31/10/2012 |
Date of 2nd request for integrations: |
17/04/2013 |
Decision Number: |
DVA-2013-002676 |
Decision Date: |
22/11/2013 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for non substantial changes |
42/288 |
06/10/2011 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/288 |
Application submission date: |
30/06/2011 |
Ministry Protocol Application submission: |
DVA - 2011 - 0016788 |
Ministry Protocol date of application submission: |
12/07/2011 |
Subject: |
modifica al piano di pavimentazione delle principali pipeway (cap.7 pag.131 PI) con misure tecniche e gestionali più appropiate |
Procedure starting date : |
06/10/2011 |
Date of request for integrations: |
31/10/2012 |
Date of 2nd request for integrations: |
09/10/2013 |
Decision Number: |
DVA-2013-0015310 |
Decision Date: |
28/06/2013 |
Decisions' Outcome: |
Emanato |
Stage of the Procedure: |
Concluded |
IPPC permit for new installation |
42/222 |
16/06/2010 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42/222 |
Application submission date: |
28/05/2010 |
Ministry Protocol Application submission: |
DVA - 2010 - 0014863 |
Ministry Protocol date of application submission: |
09/06/2010 |
Procedure starting date : |
16/06/2010 |
Decision Number: |
DVA - DEC- 2011 - 0000573 |
Decision Date: |
27/10/2011 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |
First IPPC permit for existing installation |
42 |
03/11/2006 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
42 |
Application submission date: |
30/10/2006 |
Ministry Protocol Application submission: |
DSA-2006-0028104 |
Ministry Protocol date of application submission: |
03/11/2006 |
Date of request for integrations: |
31/03/2008 |
IPPC Committee's opinion date: |
02/04/2009 |
Services Conference call date: |
29/04/2009 |
Decision Number: |
DVA - DEC - 2010 - 0000273 |
Decision Date: |
24/05/2010 |
Decisions' Outcome: |
Positivo |
Stage of the Procedure: |
Concluded |