Work: Four run-of-the-river power plants on the river Tiber: Ischiarello - Pietro Amara - Orte - Santa Lucia
Project: Run-of-the-river power plant on the river Tiber located in Orte
Description: The project involves the construction of a run-of-the-river power station of 2705 kW along the River Tiber located in the municipality of Orte (Viterbo). Orte power plant is the forth of a group of four power plants built on the River Tiber.
Developer: PROTEO srl
Project type: Hydroelectric facility
Deadline for submission of comments: 03/12/2013 mail
Other projects related to the same work: Show / Hide
Regions: Lazio
Provinces: Viterbo
Municipalities: Orte
Marine areas: None
Procedure | Procedure Code | Starting date | Stage of the procedure | ||
---|---|---|---|---|---|
Environmental Impact Assessment | 489 | 10/03/2011 | Concluded | Procedure details | Documents |